TRAFFIC ANNOUNCEMENTS

We strive to keep you informed with traffic announcements during work progress

LONG-TERM PARTIAL NIGHT LANE CLOSURE AT KG. PANDAN ROUNDABOUT.

 Start Date: 17 July 2019 | End Date: 29 October 2019.
Time : 10:00pm till 5:00am
DESCRIPTION OF WORK:
The implementation of long-term partial night lane closure at Bulatan Kg.Pandan.
Download Detail of Works

LONG-TERM NIGHT ROAD CLOSURE ON PERSIARAN KLCC NEAR “THE TROIKA”

 Start Date : 22 April 2019 | End Date: 31 August 2019.
Time : 10:00 pm till 5:00 am.
DESCRIPTION OF WORK:
Long-term night road closure on Persiaran KLCC near The Troika.
Download Detail of Works

IMPLEMENTATION OF ONE-WAY TRAFFIC FLOW ON PERSIARAN KLCC/JALAN LUMBA KUDA FROM PERSIARAN KLCC/JALAN BINJAI

 Start Date: 1 September 2018 | End Date: December 2021
DESCRIPTION OF WORK:
To facilitate the construction works for the underground MRT KLCC East Station which is part of the MRT Sg. Buloh-Serdang-Putrajaya (SSP) Line
Download Detail of Works

MRT SSP LINE TRAFFIC & ERT DEPOT ACCESS – JALAN TIGA OFF JALAN CHAN SOW LIN

DESCRIPTION OF WORK:
Depot is operational 24/7 for the Sg. Buloh-Serdang-Putrajaya (SSP) Line MRT Project.
Emergency response vehicles will be entering/exiting this building. We seek your cooperation to ensure the access to the building is not blocked
Download Detail of Works

WORKING HOURS AT S16 AMPANG PARK UNDERGROUND MRT CONSTRUCTION SITE

Start Date: 1 June 2017 | End Date: December 2021

DESCRIPTION OF WORK:

S16 Ampang Park underground MRT Station construction site will begin 24-hour operations

Download Detail of Works 

LONG-TERM CLOSURE OF PEDESTRIAN WALKWAY ON JALAN RAJA MUDA ABDUL AZIZ

Start Date: 13 December 2017 | End Date: December 2022

DESCRIPTION OF WORK:

To facilitate the construction of the S15 Kpg. Bharu North underground MRT Station of the Sg. Buloh-Serdang-Putrajaya (SSP) MRT Line

Download Detail of Works

IMPLEMENTATION OF LONG-TERM TRAFFIC MANAGEMENT PLAN ON JALAN DESA

Start Date: 21 November 2017 | End Date: 21 November 2022

DESCRIPTION OF WORK:

To facilitate the construction of MRT South Portal

Download Detail of Works

TRAFFIC ANNOUNCEMENT UPDATES FOR MRT UNDERGROUND CONSTRUCTION WORKS: MEDIUM-TERM ROAD REALIGNMENT ON EAST WEST LINK HIGHWAY (KL-SEREMBAN HIGHWAY/ SMART TUNNEL BOUNDS)

 Start Date: 20 September 2018 | End Date: 31 December 2021
DESCRIPTION OF WORK:
To facilitate the preparation works for the Sungai Buloh-Serdang-Putrajaya (SSP) MRT Project
Download Detail of Works